Results

  • Successfully stabilised and reinforced shaft foundations at the TBM portal

  • Improved the integrity of large retaining structures supporting the tunnels and ramps

  • Completed all works on schedule to support the safe delivery of Australia’s longest road tunnel

Project

Solution

  • Deployed two specialist mini piling rigs to drill 200mm diameter holes up to 40m deep through reinforced concrete piles

  • Installed high-tensile steel reinforcement cages, grouted into place to secure pile bases into the Welded Tuff rock

  • Completed post-grouting using tube-a-manchette techniques to seal pile bases and improve foundation integrity

  • Delivered additional packages of work including permanent rock bolts, temporary ground anchors, and shotcrete for retaining structures

Project

Challenges

  • Extremely hard Welded Tuff rock that standard large-diameter piles could not socket into

  • Tight tolerances for drilling within 1200mm reinforced concrete piles

  • Maintaining safety and accuracy within a congested urban construction site

  • Meeting demanding timeframes to align with tunnelling and bridge works

deep foundation micro piling for tunnel Australia

Project

Overview

The Airport Link and Busway Project was one of Australia’s largest infrastructure developments, involving 15 kilometres of tunnelling for roads, busways, and connecting ramps, as well as 25 bridges and over 7 kilometres of new road. At the time of construction, it was Australia’s longest road tunnel.


Geovert was engaged in the initial phase of the piling works at the TBM (Tunnel Boring Machine) portal, delivering precision drilling and foundation reinforcement to support the critical shaft construction.

Airport Link Micro Piling | AUS

Ground engineering and reinforcement for one of Australia’s largest tunnelling and transport projects.