Results
Highwall stabilised and access to ore body secured, ensuring safe and continuous operations.
Complex geological conditions effectively managed through engineered support and innovative equipment use.
Production maintained with minimal disruption to the mining cycle.
Collaborative execution between Geovert and the Mine Geotechnical team provided a robust long-term ground support solution.
Project
Solution
Deployed specialised drilling fleet including the High Reach Drill (HRD) and SuperBoom to maximise efficiency.
Undertook technical rope access for surface preparation and precision installation of the engineered high-tensile mesh system.
Achieved higher production rates than conventional wagon drills through HRD utilisation.
Used SuperBoom to provide extended reach and installation flexibility across the slope face.
Integrated drilling and rope access crews to deliver stability while maintaining mine cycle continuity.
Project
Challenges
Highwall instability in complex and altered geological formations.
Requirement to maintain continuity of the mining cycle while implementing support.
Restricted access conditions on a 50ft batter face.
Need for a high-production, safe alternative to conventional drilling methods.

Project
Overview
The Fortuna Sill Project at Bignham Canyone Copper Mine involved addressing complex geological conditions that threatened highwall stability and access to valuable ore reserves.
Geovert was engaged by the Mine Geotechnical team to design and deliver a ground support solution that ensured both immediate slope stability and long-term mine productivity. Leveraging advanced equipment and rope access techniques, the project provided a tailored and efficient response to altered ground conditions.