Results

  • Delivered a permanent retaining solution providing long-term slope stability and property protection.

  • Enabled progression of the Takitimu North Link Stage 1 expressway without delay to critical path activities.

  • Completed the works safely while minimising disruption to the public and local businesses.

Project

Solution

  • Installed permanent soil nails and reinforced shotcrete facing to stabilise the slope and retain ground.

  • Adopted staged excavation and construction sequencing to ensure stability throughout.

  • Used noise and dust suppression methods to mitigate community impacts.

  • Implemented robust traffic management plans to maintain safe road access during works.

  • Coordinated closely with the expressway delivery team to align construction methods and program interfaces.

Project

Challenges

  • Integration with the Takitimu North Link Stage 1 expressway programme under the NZ Upgrade Programme.

  • Constrained work area directly adjacent to a live arterial road with heavy traffic.

  • Urban setting demanded stringent environmental and community impact management.

  • Complex ground conditions required adaptable drilling and anchoring techniques.

  • Tight timelines with works forming a critical path item for the wider expressway delivery.

soil nail retaining wall construction nz

Project

Overview

As part of the Takitimu North Link Stage 1 Expressway, a major NZ Upgrade Program project, stabilisation works were required on 15th Avenue in Tauranga. To support this corridor, Geovert was engaged to construct a permanent soil nail retaining wall to stabilise the slope and protect adjacent properties while enabling safe progression of road works. 


The project required working in a constrained urban setting, adjacent to an active arterial road, while aligning with the broader expressway program’s timelines and delivery milestones.

Takitimu North Link – 15th Avenue Soil Nail Retaining Wall | NZ

Retaining wall construction enabling progress on the Takitimu North Link Stage 1 expressway