Results
Completed works on schedule across all locations
Efficient delivery reduced overall project duration
Maintained safe access for residents and road users despite difficult conditions
Demonstrated capability to deliver complex multi-site remediation under adverse circumstances
Project
Solution
Deployed wagon drills, high reach drills, and rope access to minimise earthworks requirements
Delivered full scope of techniques including soil nails, micropiles, mesh, shotcrete, and fibrecrete
Mobilised multiple crews to work simultaneously across different sites
Adopted night shift working practices to minimise traffic disruption
Project
Challenges
Steep terrain and limited access at slip locations
Works undertaken at night and during adverse weather
Sites located in bushfire zones, adding complexity to planning
Limited detour options created pressure for timely completion

Project
Overview
In 2022, the Shoalhaven region of New South Wales experienced significant slope failures following prolonged heavy rainfall, disrupting access to communities across its extensive 4,500km² road network. Multiple slips required urgent remediation to stabilise slopes and reinstate safe passage for residents and road users.
Geovert was engaged to deliver a suite of slope stabilisation solutions across several remote and difficult-to-access sites, coordinating works under challenging weather conditions and with limited detour options available to the public.