Results
Completed the installation safely and ahead of schedule despite adverse conditions
Delivered a fully engineered and rated DROPS system with minimal structural impact
Provided long-term protection against dropped-object risks with validated reliability
Project
Solution
Designed and installed a large-scale lightweight nylon netting system anchored to the façade
Engineered anchoring solution, including magnetic drilling through 200mm box sections
Applied exterior waterproofing and flashing to ensure long-term integrity of the system
Third-party engineering analysis and rating to verify compliance and safety performance
Project
Challenges
Installation restricted to a shutdown period, with a narrow winter maintenance window
Proximity to blast doors and high-pressure steam piping required precise planning
Adverse weather conditions throughout winter increased complexity and safety considerations

Project
Overview
At Fonterra’s Clandeboye site in Canterbury, poly façade panels presented a significant dropped-object risk to both personnel and equipment. Geovert was engaged to design and implement a tailored DROPS (Dropped Object Prevention Scheme) solution to mitigate the hazard. The work required careful planning to suit the existing building infrastructure, while managing operational constraints and adverse winter weather.