  • Successfully delivered the hybrid debris flow attenuator at Goldsmith Slip, with the system demonstrating its effectiveness almost immediately by capturing more than 10m³ of material shortly after installation.

  • Supported the restoration of two-way traffic past Goldsmith Slip and Snake Gully in early November 2026, reopening the road ahead of the summer holiday period.

  • Reduced mobilisation and procurement constraints by incorporating the existing High Reach Drill into the design and construction methodology, enabling a practical solution to be developed around readily available equipment.

  • Maintained an excellent safety record while working beneath an active landslide through repeated rainfall, night shifts and changing site conditions. 

  • The completed attenuator was recognised by New Zealand's Minister of Transport as a major milestone in the recovery of the Waiōweka Gorge, reflecting the successful collaboration between Geovert, Beca, Stellar Projects, Waiotahi Contractors, NZ Transport Agency Waka Kotahi and Geobrugg.

Solución del proyecto

  • Emergency rope access scaling to remove unstable material and support the initial reopening of one lane to essential traffic under piloted convoy arrangements.

  • Worked collaboratively with Beca and Geobrugg through early contractor involvement to develop a hybrid debris flow attenuator, considering the available equipment, installation methodology and site constraints from the outset.

  • Designed and installed the attenuator approximately 18m above road level, incorporating a Geobrugg T-35 barrier mounted on concrete barriers at the base. The configuration was developed to intercept falling debris while preventing excessive barrier deflection into the road during a rockfall event.

  • Deployed Geovert's High Reach Drill (HRD), already available within our equipment fleet, to undertake drilling and anchor installation on the steep slope. Extensive anchor testing was completed to verify the installed system.

  • Maintained regular inspections of slope cracks and recorded debris movement from the initial emergency response through to completion, supporting safe construction within the active landslide area.

  • Constructed a shotcrete retaining wall below road level at Snake Gully to address the underslip, coordinating these works with the broader highway recovery programme.

Desafíos del proyecto

  • The Goldsmith Slip extended approximately 110m above the highway and remained active throughout construction, with ongoing rockfall presenting significant hazards to personnel working beneath the unstable slope.

  • The scale and nature of the landslide ruled out conventional mesh systems and localised stabilisation treatments, requiring an alternative approach capable of managing substantial debris movement without compromising the road below.

  • Construction took place alongside a live state highway, with essential freight movements continuing under restricted access arrangements. Much of the work was undertaken at night to accommodate traffic and construction requirements.

  • Repeated rainfall and changing ground conditions required ongoing assessment of slope stability, including monitoring cracks and recording debris movement throughout the project.

  • Significant public and media attention, combined with tight deadlines for restoring two-way traffic, placed additional pressure on the design, procurement and construction programme.

debris flow attenuator waioweka gorge nz

Descripción general del proyecto

Following severe weather across the eastern Bay of Plenty and Tairāwhiti in January 2026, a landslip exceeding 20,000m³ at Goldsmith Slip, together with an underslip at Snake Gully, forced the closure of State Highway 2 through the Waiōweka Gorge. Geovert mobilised within 24 hours as part of the initial emergency response, undertaking rope access scaling to help restore limited access for essential traffic. This early involvement progressed into a collaborative design and construction programme with Beca and Geobrugg, delivering a hybrid debris flow attenuator at Goldsmith Slip and a shotcrete retaining wall at Snake Gully. The works formed part of the recovery of this important freight and transport connection between the Bay of Plenty and Tairāwhiti.

SH2 Waiōweka Gorge – Goldsmith Slip Landslip Remediation | NZ

Emergency landslip remediation combining innovative debris flow attenuator and specialist ground engineering to restore a highway
bottom of page