Resultados

  • Completed the extensive rockfall protection programme over 18 months, delivering engineered stabilisation across the exposed coastal cliffs adjacent to the new Seacliff Bridge.

  • Eliminated the need for road closures associated with conventional crane access, allowing other construction activities to progress while reducing traffic disruption and associated project costs.

  • Enabled the progressive launch of the bridge deck to begin earlier than planned, saving three months on the alliance's critical path. The value of this programme saving exceeded Geovert's entire cost of works on the project.

  • Successfully demonstrated the safety and effectiveness of rope access wagon drilling techniques that were relatively new to the Australian civil construction industry, earning Geovert a substantial safety bonus from the LHD Link Alliance.

  • Established a significant early milestone for Geovert in Australia, demonstrating its capability to deliver large-scale, technically demanding rockfall protection works through innovative construction methodologies and collaborative project delivery.

Solución del proyecto

  • Developed a top-down construction methodology using specialist rope access technicians and wagon drills to undertake rock bolting directly on the exposed cliff faces, eliminating the need for crane-supported access from the road below.

  • Drilled and installed approximately 3,000 linear metres of rock bolts and 5,000 m² of protective mesh to secure unstable rock faces and reduce rockfall hazards along the road and bridge alignment.

  • Applied approximately 1,000 m² of shotcrete to provide additional stabilisation in designated areas, complementing the installed rock bolts and mesh protection systems.

  • Undertook controlled drill and blast operations to remove unstable rock features that presented a hazard to the road corridor and planned bridge infrastructure.

  • Worked through the safety and regulatory challenges associated with the specialist access methodology, establishing safe systems of work for drilling and installation on exposed cliff faces.

  • Collaborated with the LHD Link Alliance to integrate the stabilisation programme with bridge construction, with the project arrangement subsequently converted into New South Wales' first geotechnical sub-alliance.

Desafíos del proyecto

  • The coastal cliffs exceeded 70 metres in height, presenting access and safety challenges for drilling and rockfall protection works on steep, exposed rock faces.

  • Rock bolting was required directly above the road at the northern bridge abutment, within the area where the new bridge deck would subsequently be launched into position, creating a critical interface with the wider construction programme.

  • Conventional crane-supported access from the road below would have required road closures and restricted construction activities, potentially delaying the bridge launch and increasing project costs.

  • The proposed rope access and wagon drilling methodology was considered unconventional in Australia at the time, attracting scrutiny from WorkCover and requiring Geovert to demonstrate that the techniques could be undertaken safely.

  • The project involved extensive drilling, mesh installation, shotcrete application and removal of unstable rock features across difficult terrain and alongside bridge construction activities.

geovert rope access rockfall protection australia

Descripción general del proyecto

In 2004, Geovert undertook its first major civil project in Australia, delivering extensive rockfall protection works as part of the Lawrence Hargrave Drive Geotechnical Sub-Alliance near Wollongong, New South Wales. The project formed part of the construction of the iconic Seacliff Bridge, requiring stabilisation of exposed coastal cliffs exceeding 70 metres in height above the road and adjacent to the new bridge alignment. Working within the LHD Link Alliance, Geovert was responsible for specialist drilling, rock bolting, mesh installation, shotcrete and controlled rock removal. The project was delivered over 18 months and became a significant milestone in Geovert's early Australian operations, demonstrating the value of specialist access methodologies on complex infrastructure projects.

Lawrence Hargrave Drive Rockfall Protection | AUS

Rockfall protection on coastal cliffs using specialist rope access and drilling techniques to accelerate bridge construction